【 Weak current College 】 fire experimental content on a regular basis, including the implementation
● Automatic fire alarm system
A) detector: using special detectors, monthly volume of 1/10, batches to add smoke or fire detector heating test, simulating fire response experiments and failure alarm test, every year to complete a full sample checks and the other detectors put into operation two years later, every three years all cleaning again, and repeat response thresholds and other necessary functions.
B) Manual alarm button, to simulate fire State response test, monthly volume of 1/10, per year to complete a full sample checks. The other probe into the second year running, every three years all cleaning again, and repeat response thresholds and other necessary functions.
C) Manual alarm button, to simulate fire State response test, monthly volume of 1/10, per year to complete a full sample checks.
D) alarm: simulating fire State response test, monthly volume of 1/10, per year to complete a full sample checks for frequent false alarm device and place for technical analysis.
E) fire alarm controller, the fail, alarm, silencers, reset, fire and memory, battery, test, once a day.
F) floor display, troubleshooting, alarm, silencers, functional test, once a day.
G) manual or automatic testing related fire control equipment for control and display functions, on the action after the adverse consequences of control functions, including water spraying extinguishing system power control section.
● Automatic (Executive) fire control system
A) flow indicator, used spray system are placed at the end of the floor water test to check whether the normal flow indicator, once per quarter.
B) wet alarm valve, open test detection alarm valve, pressure switch, electrical signals correctly, open the drain valve to check whether the normal main valve, once a day.
C) pumps, regulators pumps, automatic restart and stop normal, main pump, the alternate pump conversion is functioning properly and that once a month, the equipment used should be at the pump test displacement pump switch function.
D) fire-fighting pump valve once daily in the system all valve maintenance checks once per quarter.
E) check the pipe network system warning signs is complete.
F) fire hydrant, routine inspection, the test pressure, check the water pressure and pipe, and drop test, once a month.
G) linkage control, fire control, restart, stop the pump and check whether the normal feedback signal, once a month, the equipment used should be at the pump test displacement pump switch function.
H) on the system checks all valves, maintenance, monthly
● Smoke control system and fire service lift system
A) test automatically open smoke outlet, turn off the exhaust fan starts.
B) test of automatic turn off air conditioning system electric fire damper
C) test manually closing fire damper
D) system in all the air valve performs inspections, maintenance, monthly volume of 1/10 are checked each year to complete a full sample checks.
E) fire elevator carries on the artificial control and automatic control function test, the control signals are normal, bi-annual test time.
● Fire evacuation lighting and a dedicated distribution system
A) fire control rooms and equipment between the telephone call test, once a month.
B) phone jack press 1/10 of the total, per month, per year to complete a comprehensive inspection.
C) fire control room 119-bed, a direct dial telephone and intercom test, test each half year.
D) check the power outage can automatically switch to standby power supply.
E) test continuous life not less than 20 minutes
● Fireproofing system
A) through the fire control rooms for linkage experiment, check the device action and feedback signal is normal, half-yearly inspections.
B) test of automatic restart of fire doors, fire shutter, quarterly check the total amount of 1/4.
C) manual button starts a fire door, fireproof roller doors, check each quarter of the total 1/4.
D) starts with the emergency fire shutter sharp fall of the device, check that it is normal.
● Gas fire extinguishing system
A) carries on the artificial starts and emergency shut-off tests, test it once per quarter.
B) and fixed fire-extinguishing equipment linkage control other devices (including closing of fire doors, Windows, stop air-conditioning fans, closing fire damper, fire curtain falls) to test, test it once per quarter.
C) for each gas cylinder for weighing checks (fire extinguishing agent net weight shall be not less than 95% of design), confirm that there is no air leakage, a bi-annual test time.
D) test controller electrical components and wiring are intact, is working correctly.
E) system spray on pipeline pressure test to confirm that there is no air leakage, a bi-annual test time.
F) establishment and maintenance of fire facilities, implementing the fire facility archives daily management system, the establishment of supervised maintenance, inspection, periodic operation mechanism.