【 Weak current College 】 fire system construction program
1.0 range
This procedure applies to oil field production facility project fire system materials and equipments, inspection, installation and commissioning (fire-alarm system construction not included in this program).
2.0 reference file
Site storage and equipment protection
Pipeline design and general arrangement drawings
Pipe manufacturing
Pipe welding
Pipe outside coating of epoxy resin
Pipe transport and handling
Fire protection systems
Land-based installation works fire assessment
Fire retardant
Surface paint and coating
Process pipe welding procedures
Station technology pipeline construction program
On-site materials handling, storage and dissemination program
3.0 fire equipment inspection and storage
All fire-fighting equipment only QC engineers tested and approved by the owner authorized to transport to the site. Construction team in addition to the review of the fire-fighting equipment should be consistent with the drawings and specifications, you need to check the date of manufacture of material, ensure that all equipment in the warranty.
Spot fire equipment handling, storage and distribution see scene materials handling, storage and issuance procedures.
4.0 fire pipe installation
Fire pipe installation station process piping Setup and installation of fire on land in the assessment of requirements. In addition to the fire, permanent water connection shall not be connected to the fire water network system. Permanent water network system may not be used for electrical equipment grounding, it is especially important to DC not grounded to fire protection system on the pipeline.
Fire fighting pipes system pressure test and clean-up in accordance with the station process piping setup requirements, but must be completed prior to the test.
Fire pipeline aerial parts of paint required in accordance with 8400-A brushed.
5.0 fire pump installation
Fire pump installation program press equipment construction program execution.
Fire control pump of single trial operation and transportation procedures as a stand-alone test operation and system through program execution.
6.0 other fire facilities installation
6.1 General
Fire fighting facilities construction should strictly follow the construction drawings to arbitrarily change location. If the drawing without the fire services facilities construction owners should be in accordance with the regulatory requirements for installation.
6.2 foam system installation
6.2.1 foam breaking block installation by static equipment construction program execution, and shall conform to the drawings. Foam tank chemicals in foam system with a full test operation.
6.2.2 other foam system facilities installed to comply with the land-based installation works fire assessment requirements.
6.3 outdoor installation of fire-fighting facilities
6.3.1 fire hydrant should follow the land-based installation works fire assessment special district fire safety requirements for the installation.
6.3.2 outdoor mobile fire fighting facilities only after completion of the mechanical demands placed by drawings.
6.4 indoor installation of fire-fighting facilities
6.4.1 indoor fire facilities installed in accordance with the structure layout requirements for room fire, fire hydrant installation, you must remove the tank hose. all accessories with a water gun. Cabinet installed after recovery. Fire hydrant should install flat solid, all parts should be complete and reliable. Fire hydrant should be installed in buildings within the obvious as well as access to convenient place.
6.4.2 indoor mobile fire fighting facilities should be placed in a visible location and dates listed indicate the dosing.
6.5 install automatic fire extinguishing system see fire alarm system work procedures and instrumentation construction program
7.0 fire system debugging
7.1 fire system debugging must be completed before the system test, and that all parameters are fully meet the design requirements. Fire system debugging owners and owners of the operators should participate.
7.2 fire system pipeline before debugging should meet the following requirements;
L fire system pipeline via pressure test and clean.
L all fire-fighting accessories installed.
L test procedures and approval by the owners.
7.3 indoor hydrant acceptance should be in the water pressure in line with specifications conditions and meet the following requirements:
L working pump, the alternate pump conversion run 1-3;
L fire control room operation start pump 1-3;
More control functions manual and automatic operation should properly, and signal correctly.
7.4. foam fire extinguishing system debugging before debugging should meet the following requirements;
L foam tank cleaning closed and the owners.
L foam tank foam liquid has added full.
L test procedures and approval by the owners.
7.5 foam fire extinguishing system debugging should be consistent with the specification and drawings while logging all data.
7.6 sprinkler systems of inspection, shall conform to specifications, and do the following control functions:
L working pump and spare pump conversion run 1-3;
L fire control room operation start-up and shut-down pump 1-3;
7.7 carbon dioxide extinguishing systems before trial operation should meet the following requirements;
All system-related instruments have been adjusted.
L carbon dioxide fire extinguishing system with the school.
L test procedures and approval by the owners.
7.8 CO2 extinguishing system commissioning result shall conform to the drawings and specifications, when trial operationSecurity.
All mobile fire extinguishers in 7.9 system debugging should be full of chemicals before, and inventory of drugs.
All mobile fire extinguishers are required according to the drawing, halon, foam, dry chemical, carbon dioxide and other fire-fighting equipment should be placed in clear easy location and dates listed indicate the dressing and custodians, halon, foam, dry chemical, carbon dioxide and other fire extinguishing system for inspection, subject to the owners of the specification for sampling check failure should be replaced immediately.
8.0 construction quality records and inspection reports
8.1 construction quality records should be synchronized with the construction, correctly, a true reflection of the construction, QC engineers and technicians should regularly check the various records, construction team should have the specialist is responsible for the records.
8.2 inspection report completed by QC engineer, truly reflect the content, quality check.
8.3 construction quality records and check table see quality plan pipeline and instrument parts.
Amendments as the program 9.0 is not suitable for the purpose of completing the work of design, new construction, or the scene of new data, or the owners have new requirements, the procedure for amendment.